Toms River to Agualta Vale KFAED Road Project

Reconstruction of road alignment and re-alignment, road widening and the construction of shoulders, relocation of water, electricity and telephone utilities, construction of drainage works including surface and sub-surface drains, pavement upgrades including excavation, placement of sub-base, base and asphaltic concrete, road markings, and the installation of traffic control devices
Contract Date: 
November, 2017
Project Photos: 
Total Cost: 
JA$597M
Monday, November 6, 2017 (All day)
Completion Date: 
31 January 2019
Client: 
Government of Jamaica
Project: 
Toms River to Agualta Vale KFAED Road Project
Country: